The Tennessee Department of Transportation says work is continuing on the SR 111 J-Turn safety improvements project in Putnam County, with crews shifting to median construction and final roadway preparation, according to an announcement published Nov. 10.
TDOT says crews completed fine grading and site preparation Monday, began paving the asphalt base Tuesday, and continued paving the base and intermediate layers Wednesday and Thursday, with nighttime work intended to minimize effects on drivers.
The department says concrete median construction is expected to begin, while crews continue installing shoulder stone and grading within the project limits. Intermittent lane closures may occur as needed, TDOT says.
Over the next several weeks, the department plans to install the final asphalt layer, pavement markings, delineators and permanent signs, and to install guardrail on the project’s northwest side, according to the announcement. TDOT says the project is targeted for completion Nov. 30, 2026, weather permitting, and that schedules may change with conditions.
For updates, TDOT directs motorists to its SmartWay Map or to dial 511 for statewide travel information. The announcement lists TDOT contact information as (615) 741-2848 and TDOT.Comments@tn.gov.